Pine Grove Gas Main Work
As per an email just received from O&R.
02/22/24
Beginning this week, O&R contractor Riggs & Distler will begin a gas main replacement project in the following locations Laurel Rd, Dogwood Ter, Birch Rd, Cedar Ter, and Hazelwood Rd.
The project will last for approximately 6 weeks and consists of replacing 1700’ of 2” ST with new 2” PLX and upgrading 34 services. This project is part of the 2023 Bare Steel Replacement Program.